Construction Projects

Construction Project Updates:

Overlay Project (16th St SW & Adams Ave NW) – The Streets Department intend to have the edges milled late July or early August, and the overlay should happen shortly after that. The remaining Pedestrian ramps on Adams should be completed within the next week. The contractor was waiting on truncated domes. 

Contractors for Canadian Pacific are replacing the crossing at State Avenue. This project is anticipated to be complete by the end of the day Friday July 19th.

Street & Utility: 

Holly St. SW – The first layer (of two) of asphalt was paved on Monday (July 8), the replacement panels of sidewalk & pedestrian ramps were poured on Wednesday(July 10).

North St. NW – The first layer of asphalt was paved on Tuesday (July 9).

13th St NE – All new subbase material has been placed and graded. Some curb & pedestrian ramps will be removed and replaced. Asphalt paving is yet TBD. 

Street Maintenance (Crack seal & Seal coat): The Crack sealing is completed. The Seal-coating is completed in town, just one lot in the airport is remaining. The contractor will return in a few weeks to finish that.

CIPPS Sanitary Sewer project: The contractor has started pre-cleaning and televising the sewers.